October 1989 (36.9049 Degrees, -121.7807 Degrees) Struve Slough Bridges |
The bridge replacement was Caltrans first experiment with incentive/disincentive contracts where contractors bid on how many days it would take to rebuild the bridges. The job was completed in 55 days, 35 days earlier than expected and the contractor earned an additional $30,000 for every day they saved or an extra $1 million for early completion.
Santa Cruz County, California Bridges: State Route 1 Bridges across Struve Slough by Mark Yashinsky is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.